Safety stock is the buffer sized so demand does not run out during a lead time.

Last updated

Safety stock

32

Reorder point
272
Buffer as a share of lead time demand
13.33%

Values update as you type. This calculator covers the single scenario its formula assumes — see Common Mistakes for what it leaves out.

The formula this calculator uses

safety stock = z x demand standard deviation x sqrt(lead time)

SS
Safety stock in units
z
Service factor, 1.645 at 95 percent and 2.326 at 99 percent
sd
Standard deviation of daily demand, in units
L
Lead time in days

How to check the result by hand

  1. 1

    Decide the service level

    Ninety five percent is the usual retail target. Go higher only where a stockout is expensive, dangerous or breaches a contract.

  2. 2

    Measure the standard deviation of daily demand

    Use the same product over a comparable period. A monthly standard deviation divided by the square root of thirty is not the same thing and will give the wrong buffer.

  3. 3

    Multiply the factor by the standard deviation

    1.645 times 8 is 13.16 units. This is the buffer that would cover a single day of lead time at the target service level.

  4. 4

    Multiply by the square root of lead time

    13.16 times the square root of six is about 32 units. Random variation accumulates as a square root, so a longer lead time needs less than proportionally more.

  5. 5

    Add it to average demand during the lead time

    Forty units a day over six days is 240, and adding 32 gives a reorder point of 272. The buffer protects the service level; the reorder point decides when to order.

Common Questions

How does the Safety Stock Calculator work?

Pick the service factor for the fill rate you want, multiply it by the day to day variability in demand, then multiply by the square root of the lead time in days. A 95 percent service factor of 1.645, a standard deviation of 8 units and six days of lead time gives 32 units, on top of a reorder point of 240 units.

What do I need to enter in the Safety Stock Calculator?

It takes 4 inputs: Service level, Demand standard deviation, Lead time in days, Average daily demand. Fields that expect a unit say so next to the label.

Where does Safety stock come from?

It comes from SS = z x sd x sqrt(L) — the buffer that covers demand variability during a lead time at the target service level.

What is the most common mistake with the Safety Stock Calculator?

Confusing safety stock with the reorder point. The reorder point is average demand during the lead time plus safety stock. The buffer is only the second term, and quoting one for the other understates or overstates orders by hundreds of units.

For worked examples, common mistakes and the limits of this formula, read the full How To Calculate Safety Stock page.